Craiova Industrial Park is an investment objective that is made on the Avioane Craiova platform, on an out-of-town land totaling 10.4 Ha. This land was transferred by the Romanian Government to Dolj County for the construction of the Craiova Industrial Park by dividing the company Avioane S.A.
In order to rehabilitate the Craiova Industrial Park, it was necessary to carry out several works, which were identified, analyzed and evaluated in the feasibility study for the following investment objectives:
- Rehabilitation and use of existing buildings.
- Rehabilitation of the existing road infrastructure.
- Completion of the new road infrastructure.
- Rehabilitation of existing utilities (water, sewer, gas, cables) including their metering.
- Realization of utilities for the plots designated to host the industrial infrastructure, including their metering.
- Maintaining environmental protection indicators within the limits imposed by EU regulations. by attracting profitable businesses that promote non-polluting technologies and use the land provided in the following structure: 50% construction, 25% access roads, 25% green space.