Construction of a wind farm consisting of 3 wind turbines and related electrical connection

Feasibility study and technical project, zonal urban plan, funds access consultancy.
_MG_4943
_MG_4967
_MG_4977
_MG_5040
_MG_5196
_MG_5354
_MG_5439
_MG_5473
_MG_5575
_MG_5614

The project considered the connection to the electricity network of a wind power plant with an installed capacity of 6 MW, located in the area of ​​Mihai Bravu, Tulcea County.

Name:
Construction of a wind farm consisting of 3 wind turbines and related electrical connection
Beneficiary:
EOL ENERGY
Services:
Feasibility study and technical project; Area Town Planning; fund access consultancy
Funding source:
Environmental Fund Administration - 33% of the eligible value of the project; Bank credit line - 75% of the total value of the project; Own contribution - 25% of the total value of the project
Stage:
Completed
Location:
Tulcea County

ROMAIR CONSULTINGHeadquarters
4 Mr. Ștefan Sănătescu Str.,

District 1, Bucharest
GET IN TOUCHRomair on Social Media
ROMAIR CONSULTINGHeadquarters
4 Mr. Ștefan Sănătescu Str.,

District 1, Bucharest
OUR LOCATIONSWhere to find us?
GET IN TOUCHRomair on Social Media