The general objective of the project “Rehabilitation and modernization of the water supply and sewerage system in Ilfov county”, of which this contract is part, is to improve the infrastructure in the water and wastewater sector in the project area of Ilfov county – Bragadiru, Branești, Cernica, Ciorogârla, Cornetu, Dobroești, Domnești and Pantelimon, in order to fulfill the compliance obligations assumed by the Accession Treaty
The services provided by Romair Consulting include design services and technical assistance during the award procedures by the Beneficiary, technical assistance as a designer during the execution of works and complete services for supervising the execution of works, through specialized and authorized personnel, for 8 contracts. of works.
Link to Contracte de finanțare – APA ILFOV : APA ILFOV (acilfov.ro)
- Name:
- Technical assistance for the project "Rehabilitation and modernization of the water supply and sewerage system in Ilfov county" - Lot 1 - Project Management
- Beneficiary:
- Apă-Canal Ilfov S.A.
- Services:
- Technical Assistance for Supervision of Works and Design
- Duration:
- 59 months
- Funding source:
- POS Environment
- Stage:
- Completed
- Location:
- County Ilfov